Agler Road Sidewalks - Sunbury Road to Cassady Avenue
Share Agler Road Sidewalks - Sunbury Road to Cassady Avenue on FacebookShare Agler Road Sidewalks - Sunbury Road to Cassady Avenue on TwitterShare Agler Road Sidewalks - Sunbury Road to Cassady Avenue on LinkedinEmail Agler Road Sidewalks - Sunbury Road to Cassady Avenue link
This project consists of constructing sidewalks along Agler Rd from Sunbury Rd to Cassady Rd, along Sunbury Rd from Agler Rd north to Mifflin Middle School, and on Cassady Ave from Agler Rd north to Cassady Alternative Elementary School. Installation of the sidewalk will include curb ramps, drive approaches and signing and pavement markings. Stormwater drainage improvements will be made where necessary.
Portions of this sidewalk project are located on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. These Vision Zero safety improvements are designed to increase visibility of people walking and separate these vulnerable road users from vehicle traffic.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
This project consists of constructing sidewalks along Agler Rd from Sunbury Rd to Cassady Rd, along Sunbury Rd from Agler Rd north to Mifflin Middle School, and on Cassady Ave from Agler Rd north to Cassady Alternative Elementary School. Installation of the sidewalk will include curb ramps, drive approaches and signing and pavement markings. Stormwater drainage improvements will be made where necessary.
Portions of this sidewalk project are located on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. These Vision Zero safety improvements are designed to increase visibility of people walking and separate these vulnerable road users from vehicle traffic.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Page last updated: 17 Apr 2026, 02:53 PM
Estimated Schedule and Costs
Design
Agler Road Sidewalks - Sunbury Road to Cassady Avenue has finished this stage
Early 2023 - Late 2025
Estimated Cost: $500,000
Right-of-Way
Agler Road Sidewalks - Sunbury Road to Cassady Avenue has finished this stage
Late 2024 - Late 2025
Estimated Cost: $150,000
Private Utility Relocations
Agler Road Sidewalks - Sunbury Road to Cassady Avenue has finished this stage
Late 2024 - Summer 2025
Construction
Agler Road Sidewalks - Sunbury Road to Cassady Avenue is currently at this stage
Spring 2026* - Spring 2027*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $1.9 Million
Completed
this is an upcoming stage for Agler Road Sidewalks - Sunbury Road to Cassady Avenue