Avery Road Pavement Additions - Hayden Run Road to Avery Run Road
Share Avery Road Pavement Additions - Hayden Run Road to Avery Run Road on FacebookShare Avery Road Pavement Additions - Hayden Run Road to Avery Run Road on TwitterShare Avery Road Pavement Additions - Hayden Run Road to Avery Run Road on LinkedinEmail Avery Road Pavement Additions - Hayden Run Road to Avery Run Road link
This project will reconstruct and widen Avery Road from the CSX railroad tracks to Avery Run Road. There will be a roundabout at Avondale Woods Boulevard and a traffic signal at the intersection of Lexi Lane and Castlefinn Drive. The reconstructed roadway will be converted to a curb and gutter section with the addition of a 10’ wide shared use path along the east side, sidewalk along the west side, street lighting, and street trees. The anticipated lane configuration is two through lanes in each direction with a two-way left turn lane or dedicated left turns at intersections.
South of the railroad tracks, the existing roadway section is not anticipated to be modified with the exception of lane control modifications. Sidewalk will be extended south of the railroad tracks to Winters Run Road. Other complete street improvements south of the tracks will be determined in design following coordination with City of Hilliard and Franklin County.
The project is also anticipated to include a waterline extension along Avery Road, limits to be determined.
This project will reconstruct and widen Avery Road from the CSX railroad tracks to Avery Run Road. There will be a roundabout at Avondale Woods Boulevard and a traffic signal at the intersection of Lexi Lane and Castlefinn Drive. The reconstructed roadway will be converted to a curb and gutter section with the addition of a 10’ wide shared use path along the east side, sidewalk along the west side, street lighting, and street trees. The anticipated lane configuration is two through lanes in each direction with a two-way left turn lane or dedicated left turns at intersections.
South of the railroad tracks, the existing roadway section is not anticipated to be modified with the exception of lane control modifications. Sidewalk will be extended south of the railroad tracks to Winters Run Road. Other complete street improvements south of the tracks will be determined in design following coordination with City of Hilliard and Franklin County.
The project is also anticipated to include a waterline extension along Avery Road, limits to be determined.
Page published: 17 Apr 2026, 02:52 PM
Estimated Schedule and Costs
Study
Avery Road Pavement Additions - Hayden Run Road to Avery Run Road has finished this stage
Late 2018 - Spring 2020
Estimated Cost (Study & Design): $1.4 Million
Design
Avery Road Pavement Additions - Hayden Run Road to Avery Run Road is currently at this stage
Summer 2020 - Late 2025
Estimated Cost (Study & Design): $1.4 Million
Right-of-Way
this is an upcoming stage for Avery Road Pavement Additions - Hayden Run Road to Avery Run Road
Summer 2025 - Summer 2026
Estimated Cost: $200,000
Private Utility Relocations
this is an upcoming stage for Avery Road Pavement Additions - Hayden Run Road to Avery Run Road
Spring 2026 - Fall 2026
Estimated Cost: $300,000
Construction
this is an upcoming stage for Avery Road Pavement Additions - Hayden Run Road to Avery Run Road
Fall 2026* - Late 2028*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $17 Million
Completed
this is an upcoming stage for Avery Road Pavement Additions - Hayden Run Road to Avery Run Road