West Broad Street and Doherty Road Pavement Additions
Share West Broad Street and Doherty Road Pavement Additions on FacebookShare West Broad Street and Doherty Road Pavement Additions on TwitterShare West Broad Street and Doherty Road Pavement Additions on LinkedinEmail West Broad Street and Doherty Road Pavement Additions link
The intersection project will add a left turn lane from Broad Street to Doherty Road to improve safety at this high-crash location. Doherty Rd will be reconstructed from W Broad St to Weston Woods Dr with new curbs and a new shared-use path on the west side. A new shared-use path will be installed on the north side of W Broad St. Additional improvements to the intersection will include the installation of a new traffic signal, street lighting. These Vision Zero safety improvements are designed to increase visibility of people walking and biking, slow driver speeds, and better manage traffic flow. Stormwater drainage improvements will be made where necessary.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes and/or crashes involving vulnerable road users like people walking, biking or riding a motorcycle.
The intersection project will add a left turn lane from Broad Street to Doherty Road to improve safety at this high-crash location. Doherty Rd will be reconstructed from W Broad St to Weston Woods Dr with new curbs and a new shared-use path on the west side. A new shared-use path will be installed on the north side of W Broad St. Additional improvements to the intersection will include the installation of a new traffic signal, street lighting. These Vision Zero safety improvements are designed to increase visibility of people walking and biking, slow driver speeds, and better manage traffic flow. Stormwater drainage improvements will be made where necessary.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes and/or crashes involving vulnerable road users like people walking, biking or riding a motorcycle.
Page last updated: 17 Apr 2026, 02:55 PM
Estimated Schedule and Costs
Design
West Broad Street and Doherty Road Pavement Additions has finished this stage
Late 2020 - Late 2023
Utility Relocations
West Broad Street and Doherty Road Pavement Additions has finished this stage
Early 2022 - Spring 2024
Right-of-Way
West Broad Street and Doherty Road Pavement Additions has finished this stage
Summer 2023 - Summer 2024
Estimated Cost: $150,000
Construction
West Broad Street and Doherty Road Pavement Additions is currently at this stage
Winter 2024 - Spring 2026*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $3.2 Million
Completed
this is an upcoming stage for West Broad Street and Doherty Road Pavement Additions