Cleveland Avenue at Hudson Street - Intersection Safety Improvements
Share Cleveland Avenue at Hudson Street - Intersection Safety Improvements on FacebookShare Cleveland Avenue at Hudson Street - Intersection Safety Improvements on TwitterShare Cleveland Avenue at Hudson Street - Intersection Safety Improvements on LinkedinEmail Cleveland Avenue at Hudson Street - Intersection Safety Improvements link
The intersection project at Cleveland Ave and Hudson St will improve this high-crash location by adding northbound and southbound turn lanes and a westbound right turn lane. New sidewalk will be installed. The shared-use path recently constructed on the south side of Hudson St will be extended to Cleveland Ave to provide a connection to the existing path on Hudson east of Cleveland. The intersection traffic signals will be reconstructed to improve visibility.
The Ohio Department of Transportation managed the project design and right-of-way acquisition phases, and the Department of Public Service is managing construction of the safety improvements.
The improvements under construction have been designed to mitigate the high number of rear-end, angle and sideswipe-passing crashes. The intersection was identified on the Governor’s Top 150 list of priority intersections, and ODOT safety funding was allocated to make improvements that reduce crashes.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. The location is also a Vision Zero Priority Intersection identified for safety improvements.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
The intersection project at Cleveland Ave and Hudson St will improve this high-crash location by adding northbound and southbound turn lanes and a westbound right turn lane. New sidewalk will be installed. The shared-use path recently constructed on the south side of Hudson St will be extended to Cleveland Ave to provide a connection to the existing path on Hudson east of Cleveland. The intersection traffic signals will be reconstructed to improve visibility.
The Ohio Department of Transportation managed the project design and right-of-way acquisition phases, and the Department of Public Service is managing construction of the safety improvements.
The improvements under construction have been designed to mitigate the high number of rear-end, angle and sideswipe-passing crashes. The intersection was identified on the Governor’s Top 150 list of priority intersections, and ODOT safety funding was allocated to make improvements that reduce crashes.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. The location is also a Vision Zero Priority Intersection identified for safety improvements.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Page last updated: 17 Apr 2026, 03:12 PM
Estimated Schedule and Costs
Study
Cleveland Avenue at Hudson Street - Intersection Safety Improvements has finished this stage
Early 2020 - Summer 2021
Estimated Cost: $150,000
Design
Cleveland Avenue at Hudson Street - Intersection Safety Improvements has finished this stage
Late 2021 - Spring 2024
Estimated Cost: $650,000
Right-of-Way
Cleveland Avenue at Hudson Street - Intersection Safety Improvements has finished this stage
Late 2022 - Spring 2024
Estimated Cost: $1.5 Million
Utility Relocations
Cleveland Avenue at Hudson Street - Intersection Safety Improvements has finished this stage
Spring 2024 - Early 2025
Construction
Cleveland Avenue at Hudson Street - Intersection Safety Improvements is currently at this stage
Summer 2024 - Late 2025*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $5 Million
Completed
this is an upcoming stage for Cleveland Avenue at Hudson Street - Intersection Safety Improvements