Dublin-Granville Road at Ulry Road - Intersection Safety Improvements
Share Dublin-Granville Road at Ulry Road - Intersection Safety Improvements on FacebookShare Dublin-Granville Road at Ulry Road - Intersection Safety Improvements on TwitterShare Dublin-Granville Road at Ulry Road - Intersection Safety Improvements on LinkedinEmail Dublin-Granville Road at Ulry Road - Intersection Safety Improvements link
This project will make safety improvements to the intersection at Dublin-Granville Road at Ulry Road, and will improve connectivity for people walking and biking in the area. The improvements include adding eastbound and westbound turn lanes on Dublin-Granville Road. Dublin-Granville Road will also be widened and reconstructed between Ulry and Old Hamilton Road to accommodate a two-way left turn lane. A new mast arm traffic signal and street lighting will be installed at the intersection to improve visibility for all road users. Other improvements will include replacement of the existing sidewalk, curb, street trees and shared-use path (SUP). The SUP will be extended to approximately 100' west of Conifer Drive for a future tie-in to the Blendon Woods Metro Park. These Vision Zero safety improvements will improve drivers’ visibility of pedestrians and bicyclists and safely separate these vulnerable road users from vehicle traffic. Storm sewer improvements will be made as needed.
This project will make safety improvements to the intersection at Dublin-Granville Road at Ulry Road, and will improve connectivity for people walking and biking in the area. The improvements include adding eastbound and westbound turn lanes on Dublin-Granville Road. Dublin-Granville Road will also be widened and reconstructed between Ulry and Old Hamilton Road to accommodate a two-way left turn lane. A new mast arm traffic signal and street lighting will be installed at the intersection to improve visibility for all road users. Other improvements will include replacement of the existing sidewalk, curb, street trees and shared-use path (SUP). The SUP will be extended to approximately 100' west of Conifer Drive for a future tie-in to the Blendon Woods Metro Park. These Vision Zero safety improvements will improve drivers’ visibility of pedestrians and bicyclists and safely separate these vulnerable road users from vehicle traffic. Storm sewer improvements will be made as needed.
Page last updated: 17 Apr 2026, 03:08 PM
Estimated Schedule and Costs
Design
Dublin-Granville Road at Ulry Road - Intersection Safety Improvements has finished this stage
Spring 2023 - Early 2024
Estimated Cost: $58,000
Construction
Dublin-Granville Road at Ulry Road - Intersection Safety Improvements has finished this stage
Summer 2024* - Late 2024*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $110,000
Completed
Dublin-Granville Road at Ulry Road - Intersection Safety Improvements is currently at this stage