Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue
Share Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue on FacebookShare Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue on TwitterShare Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue on LinkedinEmail Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue link
This project will construct a shared-use path (SUP) from S. Wayne Avenue through Hilltonia Park to Whitethorne Avenue on the north side of Eakin Road, and a crosswalk at the intersection of Whitethorne Avenue. This project will connect to existing SUP on the south side of Eakin Road from Whitethorne Avenue to Harrisburg Pike.
This SUP project is located on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. This Vision Zero safety improvement will increase visibility of people walking and biking and separate these vulnerable road users from vehicle traffic.
This project will construct a shared-use path (SUP) from S. Wayne Avenue through Hilltonia Park to Whitethorne Avenue on the north side of Eakin Road, and a crosswalk at the intersection of Whitethorne Avenue. This project will connect to existing SUP on the south side of Eakin Road from Whitethorne Avenue to Harrisburg Pike.
This SUP project is located on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. This Vision Zero safety improvement will increase visibility of people walking and biking and separate these vulnerable road users from vehicle traffic.
Page last updated: 17 Apr 2026, 02:50 PM
Estimated Schedule and Costs
Study
Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue has finished this stage
Spring 2021 - Early 2022
Design
Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue is currently at this stage
Summer 2023 - Summer 2025
Estimated Cost: $650,000
Right-of-Way
this is an upcoming stage for Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue
Early 2025 - Spring 2026
Estimated Cost: $350,000
Private Utility Relocations
this is an upcoming stage for Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue
Early 2025 - Spring 2026
Construction
this is an upcoming stage for Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue
Summer 2026* - Late 2028*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $3.5 Million
Completed
this is an upcoming stage for Eakin Road Shared Use Path - Wayne Avenue to Whitethorne Avenue