Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue
Share Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue on FacebookShare Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue on TwitterShare Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue on LinkedinEmail Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue link
This project will install a new shared use path (SUP) along the east side of Georgesville Road from Parkwick Drive to Sullivant Avenue (south leg, west of Georgesville Road). In addition to the SUP, the project will install curb ramps, drive aprons, sidewalk along the west side of Georgesville Road at select locations, street lighting, and curb and storm sewer as needed. This project will also install sidewalk and curb ramps along the north side of Parkwick Drive to fill gaps between Georgesville Road and Bay Club Drive. The striping configuration and pavement width at the bridge over Scioto Big Run will be modified to provide a narrower roadway section in order to accommodate a shared use path along the east side and sidewalk along the west side. Additionally, Georgesville Road will be resurfaced from the north side of the Georgesville Road bridge over IR-270 to the City of Columbus corporation limit north of Camp Chase Railroad crossing.
This project will install a new shared use path (SUP) along the east side of Georgesville Road from Parkwick Drive to Sullivant Avenue (south leg, west of Georgesville Road). In addition to the SUP, the project will install curb ramps, drive aprons, sidewalk along the west side of Georgesville Road at select locations, street lighting, and curb and storm sewer as needed. This project will also install sidewalk and curb ramps along the north side of Parkwick Drive to fill gaps between Georgesville Road and Bay Club Drive. The striping configuration and pavement width at the bridge over Scioto Big Run will be modified to provide a narrower roadway section in order to accommodate a shared use path along the east side and sidewalk along the west side. Additionally, Georgesville Road will be resurfaced from the north side of the Georgesville Road bridge over IR-270 to the City of Columbus corporation limit north of Camp Chase Railroad crossing.
Page last updated: 17 Apr 2026, 02:46 PM
Estimated Schedule and Costs
Study
Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue has finished this stage
Summer 2021 - Late 2022
Design
Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue has finished this stage
Early 2023 - Spring 2025
Estimated Cost: $750,000
Right-of-Way
Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue is currently at this stage
Late 2024 - Late 2025
Estimated Cost: $150,000
Construction
this is an upcoming stage for Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue
Early 2026* - Early 2027*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $5.7 Million
Completed
this is an upcoming stage for Georgesville Road Shared Use Path - Parkwick Drive to Sullivant Avenue