Located on Livingston Ave from 18th St to Nelson Rd, this project will reduce Livingston Ave from two lanes in each direction to one lane in each direction with a center turn lane to curb excessive speeding, improve safety, and traffic flow throughout the corridor.
Other enhancements will include Vision Zero safety elements such as upgraded pedestrian crossings, improved sidewalks, protected bike lanes, curb extensions or “bump outs,” vegetated medians with street trees and a new smart street lighting system. The offset at the intersection of Livingston Ave and Fairwood Ave will be softened. These improvements are designed to slow driver speeds, increase visibility of people walking and biking and separate these vulnerable road users from vehicle traffic.
New utility poles, a water main replacement (from Ohio Ave to Nelson Rd) and improvements to the storm sewer system will also be installed.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Located on Livingston Ave from 18th St to Nelson Rd, this project will reduce Livingston Ave from two lanes in each direction to one lane in each direction with a center turn lane to curb excessive speeding, improve safety, and traffic flow throughout the corridor.
Other enhancements will include Vision Zero safety elements such as upgraded pedestrian crossings, improved sidewalks, protected bike lanes, curb extensions or “bump outs,” vegetated medians with street trees and a new smart street lighting system. The offset at the intersection of Livingston Ave and Fairwood Ave will be softened. These improvements are designed to slow driver speeds, increase visibility of people walking and biking and separate these vulnerable road users from vehicle traffic.
New utility poles, a water main replacement (from Ohio Ave to Nelson Rd) and improvements to the storm sewer system will also be installed.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Page last updated: 17 Apr 2026, 02:45 PM
Estimated Schedule and Costs
Design
Livingston Avenue - 18th Street to Nelson Road has finished this stage
Spring 2023 - Late 2025
Estimated Cost: $2.9 Million
Right-of-Way
Livingston Avenue - 18th Street to Nelson Road is currently at this stage
Late 2025 - Late 2026
Estimated Cost: $2.1 Million
Utility Relocations
this is an upcoming stage for Livingston Avenue - 18th Street to Nelson Road
Late 2025 - Late 2026
Construction
this is an upcoming stage for Livingston Avenue - 18th Street to Nelson Road
Early 2027* - Late 2028*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $35 Million
Completed
this is an upcoming stage for Livingston Avenue - 18th Street to Nelson Road