Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure
Share Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure on FacebookShare Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure on X (formerly Twitter)Share Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure on LinkedinEmail Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure link
A 2022 ODOT safety study of the high-crash intersection at Courtright Road and E Livingston Avenue found that 46% of all crashes at this location resulted in injury, nearly double the state average of 25%. As a result, this location was selected for a "quick build" test project to reduce the frequency and severity of left-turn and rear-end crashes. The materials and traffic control tools used in test projects allow for design and installation of roadway safety projects to occur sooner than new infrastructure construction takes.
This project will install water barriers along E Livingston Ave to close the right-hand turn lane leading up to the intersection at Courtright Rd. Narrowing the roadway will reduce speeding and erratic driver behavior.
The test project will be evaluated through before-and-after speed data, field observations, crash monitoring, pedestrian behavior assessments and user feedback. Results will determine whether lanes should be reconfigured or other safety improvements should be implemented.
This project is located on the Vision Zero Columbus High Injury Network and has been identified as a Vision Zero Priority Intersection due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Before: A 1,000-foot right-hand turn lane along E Livingston Avenue leading up to the high-crash intersection at Courtright RoadAfter: Water barriers close the right-hand turn lane
A 2022 ODOT safety study of the high-crash intersection at Courtright Road and E Livingston Avenue found that 46% of all crashes at this location resulted in injury, nearly double the state average of 25%. As a result, this location was selected for a "quick build" test project to reduce the frequency and severity of left-turn and rear-end crashes. The materials and traffic control tools used in test projects allow for design and installation of roadway safety projects to occur sooner than new infrastructure construction takes.
This project will install water barriers along E Livingston Ave to close the right-hand turn lane leading up to the intersection at Courtright Rd. Narrowing the roadway will reduce speeding and erratic driver behavior.
The test project will be evaluated through before-and-after speed data, field observations, crash monitoring, pedestrian behavior assessments and user feedback. Results will determine whether lanes should be reconfigured or other safety improvements should be implemented.
This project is located on the Vision Zero Columbus High Injury Network and has been identified as a Vision Zero Priority Intersection due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Before: A 1,000-foot right-hand turn lane along E Livingston Avenue leading up to the high-crash intersection at Courtright RoadAfter: Water barriers close the right-hand turn lane
Share What do you think about this safety improvement? on FacebookShare What do you think about this safety improvement? on X (formerly Twitter)Share What do you think about this safety improvement? on LinkedinEmail What do you think about this safety improvement? link
Page last updated: 19 Jul 2026, 05:15 PM
Installation
Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure has finished this stage
June 29, 2026
Project Evaluation
Livingston Avenue and Courtright Road Test Project - Right Turn Lane Closure is currently at this stage