This project consists of constructing sidewalks along the south side of Olive Street from Powell Avenue to Harris Avenue, the north side of Olive Street from Harris Avenue to Wayne Avenue, and on the south side of Floral Avenue from Oakley Avenue to Highland Avenue. Installation of the sidewalk will include curb ramps and drive approaches.
This sidewalk project intersects a portion of Wayne Avenue, which is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. This Vision Zero safety improvement will improve drivers’ visibility of pedestrians and safely separate these vulnerable road users from vehicle traffic.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
This project consists of constructing sidewalks along the south side of Olive Street from Powell Avenue to Harris Avenue, the north side of Olive Street from Harris Avenue to Wayne Avenue, and on the south side of Floral Avenue from Oakley Avenue to Highland Avenue. Installation of the sidewalk will include curb ramps and drive approaches.
This sidewalk project intersects a portion of Wayne Avenue, which is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle. This Vision Zero safety improvement will improve drivers’ visibility of pedestrians and safely separate these vulnerable road users from vehicle traffic.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Page published: 17 Apr 2026, 03:00 PM
Estimated Schedule and Costs
Design
Olive Street and Floral Avenue Sidewalks has finished this stage
Late 2018 - Spring 2024
Estimated Cost: $350,000
Right-of-Way
Olive Street and Floral Avenue Sidewalks has finished this stage
Spring 2022 - Early 2024
Estimated Cost: $90,000
Utility Relocations
Olive Street and Floral Avenue Sidewalks has finished this stage
Spring 2022 - Summer 2024
Construction
Olive Street and Floral Avenue Sidewalks has finished this stage
Summer 2024 - Late 2025*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $1.22 Million
Completed
Olive Street and Floral Avenue Sidewalks is currently at this stage