Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard
Share Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard on FacebookShare Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard on TwitterShare Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard on LinkedinEmail Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard link
This project will involve resurfacing, the addition of a southbound right turn lane and the extension of Westbourne Ave between Taylor Station Road and Blossom Field Blvd. Improvements along the extension will include new pavement, curb and gutter, drives, storm sewer system, signs and waterline. New sidewalk, shared-use path and roadway lighting will also be installed. These Vision Zero safety improvements will improve drivers’ visibility of pedestrians and bicyclists and physically separate these vulnerable road users from vehicle traffic. A roundabout will be placed at the intersection of Corrina Drive to reduce drivers’ speed and the severity of crashes at this intersection.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
This project will involve resurfacing, the addition of a southbound right turn lane and the extension of Westbourne Ave between Taylor Station Road and Blossom Field Blvd. Improvements along the extension will include new pavement, curb and gutter, drives, storm sewer system, signs and waterline. New sidewalk, shared-use path and roadway lighting will also be installed. These Vision Zero safety improvements will improve drivers’ visibility of pedestrians and bicyclists and physically separate these vulnerable road users from vehicle traffic. A roundabout will be placed at the intersection of Corrina Drive to reduce drivers’ speed and the severity of crashes at this intersection.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
It is also located in a Vision Zero Communities of Interest area. Residents in Communities of Interest may have fewer choices about how, when and where they travel, putting them at higher risk as they move around. Extra investment in roadway and other transportation safety improvements may be needed to enhance safety.
Page published: 17 Apr 2026, 02:55 PM
Estimated Schedule and Costs
Study
Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard has finished this stage
Late 2020 - Spring 2022
Estimated Cost: $250,000
Design
Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard has finished this stage
Late 2021 - Late 2023
Estimated Cost: $950,000
Right-of-Way
Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard has finished this stage
Late 2022 - Spring 2024
Estimated Cost: $500,000
Construction
Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard is currently at this stage
Spring 2024 - Late 2025*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $8.7 Million
Completed
this is an upcoming stage for Westbourne Avenue Phase 1 Extension - Taylor Station Road to Blossom Field Boulevard