Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue
Share Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue on FacebookShare Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue on TwitterShare Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue on LinkedinEmail Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue link
This project will convert Blossom Field Blvd to a public street and upgrade the roadway to meet standards, with new streetlights and curb and pavement repairs. It will enable Blossom Field to be connected to the new Westbourne Ave extension from Taylor Station Rd currently being constructed by the city. This project aims to help divert traffic volume and create safer conditions on westbound E Broad St that intend to go north on Taylor Station Rd and southbound Taylor Station traffic that wants to travel east on Broad St.
The project also serves as the second phase of the Westbourne Ave extension. A shared-use path will be constructed along the east side of Blossom Field and sidewalk along the west side to fill gaps. These new facilities for safe walking and biking will create connectivity to the new shared-use path and sidewalk being constructed in the East Broad Street arterial rehabilitation project, Phases 1 and 2. A roundabout at Blossom Field and Westbourne Ave will help to slow driver speeds and decrease crash severity.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
This project will convert Blossom Field Blvd to a public street and upgrade the roadway to meet standards, with new streetlights and curb and pavement repairs. It will enable Blossom Field to be connected to the new Westbourne Ave extension from Taylor Station Rd currently being constructed by the city. This project aims to help divert traffic volume and create safer conditions on westbound E Broad St that intend to go north on Taylor Station Rd and southbound Taylor Station traffic that wants to travel east on Broad St.
The project also serves as the second phase of the Westbourne Ave extension. A shared-use path will be constructed along the east side of Blossom Field and sidewalk along the west side to fill gaps. These new facilities for safe walking and biking will create connectivity to the new shared-use path and sidewalk being constructed in the East Broad Street arterial rehabilitation project, Phases 1 and 2. A roundabout at Blossom Field and Westbourne Ave will help to slow driver speeds and decrease crash severity.
This location is on the Vision Zero Columbus High Injury Network due to the number of serious or fatal crashes, and/or crashes involving vulnerable road users like people walking, biking or on a motorcycle.
Page last updated: 17 Apr 2026, 03:36 PM
Estimated Schedule and Costs
Design
Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue has finished this stage
Late 2023 - Summer 2025
Estimated Cost: $300,000
Right-of-Way
Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue is currently at this stage
Late 2024 - Early 2026
Estimated Cost: $100,000
Private Utility Relocations
this is an upcoming stage for Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue
Early 2025 - Early 2026
Construction
this is an upcoming stage for Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue
Spring 2026* - Summer 2027*
*Subject to funding approval by City Council and weather conditions
Estimated Cost: $5.1 Million
Completed
this is an upcoming stage for Blossom Field Boulevard Safety Improvements - East Broad Street to Westbourne Avenue